Bill of Materials and Routing

The structure and usages of a bill of material, what a routing defines, and how both feed costing.

Open contents

The bill of material and the routing are the two principal PP masters. One says what a product is made from, the other how it is made. Neither MRP nor costing works without both.

Bills of material

Key BOM fields
FieldContent
Base quantityHow many units the component quantities relate to
Components and quantitiesWhat is needed and how much
Item categoryStock item (L), non-stock (N), text (T)
ScrapExpected component and operation scrap percentages
ValidityThe period this structure applies to
Alternative itemsSubstitutes where the main component is unavailable

The base quantity matters: five units of component A against a base quantity of 100 means 0.05 per finished unit. It preserves precision where recipes do not divide evenly.

BOM usage

UsageNumberPurpose
Production1The structure MRP and manufacturing use
Engineering2The design view, by function
Universal3Shared across purposes
Sales5Kit structures for selling
Costing6A structure specifically for costing

Low-level codes

BOMs are hierarchical: product A uses semi-finished B, which uses component C. The low-level code records that depth, and both MRP and costing process in that order so that lower results feed higher ones.

Routings

What a routing contains
ElementContent
OperationOne step of work, executed in number order
Work centreWhere the operation is performed
Standard valuesSetup, machine and labour times
Control keyWhether confirmation is required, whether it is costed, whether it is external
Component allocationWhich components are used at which operation
Inspection characteristicsWhere QM is integrated

Standard values and activity types

Deriving conversion cost
Operation 10: setup   0.5 h x 3,000 =  1,500
Operation 10: machine 2.0 h x 5,000 = 10,000
Operation 10: labour  2.0 h x 2,500 =  5,000
-------------------------------------------
Conversion cost for operation 10      16,500

Standard values are multiplied by the activity rates on the cost centre behind the work centre. This is exactly where CO activity types meet PP.

Production versions

A production version pairs a specific BOM with a specific routing โ€” BOM 1 with routing A on the volume line, BOM 2 with routing B for prototypes. MRP and costing select a version to work with. S/4HANA requires production versions, so migrating from ECC means creating them.

๐Ÿ“– Unfamiliar term? Look it up in the SAP glossary.

Check your understanding

Test what you just read.

Quiz 1

Which transaction creates a Bill of Materials (BOM)?

Quiz 2

A Routing includes the standard time for each operation.

Quiz 3

What is the purpose of setting a "Validity Period" on a BOM component?

Quiz 4

BOMs support multi-level structures (semi-finished โ†’ components โ†’ raw materials).