Section 10 of 10

Project Reporting and Analysis

The PS information system, hierarchy and line item reports, and earned value management.

Open contents

Managing a project means knowing where it stands. PS offers several reporting routes for different purposes.

Two families of report

FamilyContentTransactions
Structure information systemStructure and attributesCN41 / CN42N / CN43N
Cost reportsPlan, budget, actual and commitmentCJE0 / S_ALR_87013532
Line item reportsIndividual documentsCJI3 / CJI5 / CJI8

Cost reports

Figures to compare
FigureMeaning
BudgetThe approved ceiling
Planned costThe expected total
Actual costWhat has been incurred
CommitmentOrdered but not yet incurred
Assigned valueActual plus commitment
Remaining budgetBudget less assigned value

A negative remaining budget means the overrun has already happened or is now certain. Reviewing it regularly is the essence of project cost control.

Earned value management

EVM measures
MeasureCodeMeaning
Planned valuePVBudgeted cost of work scheduled by now
Earned valueEVBudgeted cost of work actually completed
Actual costACWhat was actually spent
Cost varianceCVEV minus AC; positive is under budget
Schedule varianceSVEV minus PV; positive is ahead
Cost performance indexCPIEV over AC; below 1 means overspending
Schedule performance indexSPIEV over PV; below 1 means late
Reading the numbers
PV = 10.0m  (10.0m of work should be complete by now)
EV =  8.0m  (8.0m of work is actually complete)
AC = 12.0m  (12.0m has been spent)

CV = 8.0 - 12.0 = -4.0m  (4.0m over)
SV = 8.0 - 10.0 = -2.0m  (2.0m behind)
CPI = 8.0 / 12.0 = 0.67
SPI = 8.0 / 10.0 = 0.80

-> behind schedule and over budget

๐Ÿ“– Unfamiliar term? Look it up in the SAP glossary.

Check your understanding

Test what you just read.

Quiz 1

What is the transaction code for the Project Information System?

Quiz 2

Which is NOT one of the three Earned Value Analysis metrics?

Quiz 3

A CPI (Cost Performance Index) greater than 1.0 indicates the project is within budget.

Quiz 4

What is the correct formula for SPI (Schedule Performance Index)?

Quiz 5

PS standard reports cannot compare planned and actual costs.

Quiz 6

Arrange the Earned Value Analysis steps in order.

Click items in the correct order